Work to Start on Haslingfield/Wimpole Road Pavement

Good Morning,

We’ll be starting the Barton LHI works with de-vegetation on the Haslingfield Road Junction on the 15th March. This will be only for 1 day and with minimal disruption to traffic.

Following this the preliminary dates to start the Signs and Lining is the 23/03 and to start the Civil’s Footpath works is the 28/03, these 2 days are dependent on road space however and I will send out a letter and further email as soon as I have confirmation.

Kind Regards,

 

James Chapman

Assistant Engineer

Highway Projects and Road Safety

Cambridge City and South Team

Cambridgeshire Highways